"NYC Subway Platform Screen Doors update
Posted by Gold_12th on Mon Nov 17 14:17:59 2014
Today's board meeting reveal:
MTA and third party contractor "STV Inc." is doing an engineer study on the platform screen doors. The contract awarded in September for $25 million ( which they also doing engineering Sandy fortify projects )
There are lots of complex engineering issues like the car fleet, station layout, spacing, clearance, timing, power, ventilation, maintenance, etc.
They will demo the PSDs on one station.
To sum up... there's "not one solution." "